Assembling the Kimbo team
Project 
				Civil, Electrical and Mechanical Installation of the Kimbo system
Place 
				Cananea, Mexico
Start date
				April 2021
Activities
				- Earthmoving, platform construction by compaction at Proctor 95%
 - Laying of steel reinforcement, concrete casting f'c = 300 kg/cm² fast strength
 - Laying and levelling of base beam structure, physical ground construction
 - construction of rainwater absorption wells, mechanical assembly of the Kimbo® system