Activities
  • Installation of supply pipes from the collection
  • Flocculation tank construction, reinforced concrete f'c=300 kg/cm²
  • Construction of cylindrical, reinforced concrete sedimentation tanks f'c=300 kg/cm²
  • Construction of cylindrical filtration tanks, reinforced concrete f'c=300 kg/cm²
  • Flocculation tank construction, reinforced concrete f'c=300 kg/cm²
  • Electromechanical equipment and operational tests of the water treatment plant